New Pool Facility (Under construction)

This is considered the most exciting project at our hot springs.  A world-class facility designed to put the Yukon on the world map of great hot springs. Imagine authentic Japanese Onsen pools combined with the renowned Nordic Spas from northern Europe. Its never been done, but are determined to be the first such facility in the world….    Two saunas, two steam rooms, relax room, ample outdoor deck areas, outdoor showers, a “club mud”, and several authentic Japanese hot pools filled with unadulterated artesian-sourced thermal springs water. And of course, those challenging cold plunges and cold showers to get your circulation going in full form! It will be a cleansing experience like no other. And you will have the choice between a simple entry to the hot pools, or a full entry to hot pools, steam rooms, sauna and relax room. We will be open 365, from noon to 10pm with extended hours in the summer. Keep watching for more news!

Keep abreast of the construction of our new pool facility season by season, until the Grand Opening, slated for September, 2018.

Summer 2017

  • anticipated start of construction of new pool facility main building
  • anticipated installation of underground electrical, telephone & internet
  • other construction activities as set out in construction schedule

Winter, Spring 2017

  • detailed design for new pool facility, including all engineering design
  • projected completion of pool permitting process
  • late winter clearing of valley for 2nd evaporation pond

Fall, 2016

  • Water LIcense renewed
  • YESAB application approved
  • planning for new underground high voltage lines, telephone & internet

Summer, 2016

  • Construction of 1 hectare perimeter fence around new hot pool facility
  • Submission of Water Board application to renew water license for new facility
  • Discussions with Environmental Health on new pool design for new facility
  • Layout of new electrical lines for new facility
  • Design for Roundabout entrance for connection to new pool access road

Spring, 2016

  • Clearing for new forest access to pools & parking area
  • Completion of 3.7km. perimeter trail at Takhini Hot Springs
  • Grading of Tufa Plateau
  • Submission of YESAB proposal

Winter, 2016

  • Completion of drain line

Fall, 2015

  • Construction of drain line from source
  • Clearing in valley in order to restore historic water channel

Summer, 2015

  • Construction of new insulated pipe-line from source to new pools

Springs, 2015

  • Source restoration, removal of shed over pool, relining of crater with rock
  • Removal of gravel parking lot from Tufa plateau as part of plateau restoration

2012-2014

  • Business Plan Development, financing model, building the existing hot pool business in order to support viability of proposed new pool facility

2009 -2012

  • Participation in Yukon Business Development Program and expert verification of concepts for new pool facility